Planned shutdown — Chemical
How do you prepare a maintenance shutdown in a chemical plant?
Before any mechanical work, equipment is drained, purged and decontaminated, and process lines are isolated: valves locked out and, where needed, blind flanges installed. Tanks and reactors are often confined spaces: the RSST (ss. 297 to 312) then requires the hazards and prevention measures to be determined in writing by a qualified person, with an attendant and a rescue plan.
Which documents should be consulted before the work?
The safety data sheets (WHMIS) for the products present, the lockout procedure for each piece of equipment and the facility's permits: hot work, confined space and work at height.
Preventive maintenance — Chemical
What is checked during preventive maintenance in a chemical environment?
Corrosion and wear of tanks and piping, the condition of gaskets, pumps and agitators, and fouling of heat exchangers and cyclones. Replacement materials are chosen with the products handled in mind.
Corrective maintenance — Chemical
How do you repair a leak or corroded equipment?
We isolate and decontaminate the section, find the cause (corrosion, fatigue, wrong material), then repair or replace with a compatible material. Our welders are certified by the Canadian Welding Bureau (CWB).
Welding — Chemical
What requirements apply to welding in a chemical plant?
The choice of alloy and filler metal depends on the chemicals present. Steel structures follow the CSA W59 standard. For pressure piping, specific requirements apply, including registered welding procedures: we verify them with you before any work.
Hot work permit — Chemical
How is hot work carried out where flammable products are present?
The atmosphere is measured with a calibrated gas detector before and during the work. No work is done if flammable vapours are detected. Drains, sewers and openings are covered, and the fire watch stays in place for the entire duration of the work.
What does a hot work permit contain?
The location and validity period (no longer than the work shift), a description of the work, the checks made before starting, the name of the fire watch and the signatures. Combustible materials are removed or protected within a 15 m radius. After the work, the fire watch stays in place for at least 1 hour, then the area is checked periodically for at least 4 hours in total. You can download our template below. See also: preventive maintenance and industrial staffing in Greater Montreal.
Permit templates to download
Sources
- Règlement sur la santé et la sécurité du travail (Regulation respecting occupational health and safety) (RSST), CQLR c. S-2.1, r. 13 — lockout (ss. 188.1 to 188.13), confined spaces (ss. 297 to 312), fall protection (ss. 33.2, 33.3 and 346 to 354)
- Décret 43-2023 (Order in Council 43-2023) amending the RSST (confined spaces), Gazette officielle du Québec, January 25, 2023 — in force July 25, 2023
- CSA Z1006 — Management of work in confined spaces
- APSAM — Lockout and other energy control methods: regulations
- ASP Construction — Hot work permit (template, 2023)
- Port of Québec — Hot work framework program (references: National Fire Code, NFPA 51B, CSA W117.2)
- NFPA 51B — Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
- CSA W117.2 — Safety in welding, cutting and allied processes
- CSA W59 — Welded steel construction; CSA W47.1 — Certification of welding companies (Canadian Welding Bureau)
- Code de sécurité (Safety Code), chapitre VIII — Bâtiment (Chapter VIII — Building), CQLR c. B-1.1, r. 3, which incorporates the National Fire Code — Canada 2010 (amended)