Planned shutdown — Pharmaceutical
How does a planned shutdown work in a pharmaceutical plant?
The work follows your change control: every modification is approved in advance, documented and carried out according to the gowning and access procedures of your areas. We prepare the list of materials, parts and methods so that your validation team can plan the requalification of the affected equipment.
Preventive maintenance — Pharmaceutical
Why is preventive maintenance essential in a GMP environment?
Health Canada's good manufacturing practices (GUI-0001) require equipment to be maintained under a written program and interventions to be recorded. We provide a log of every intervention and, for product-contact parts, the material certificates that ensure traceability.
Corrective maintenance — Pharmaceutical
What happens after an unplanned repair on GMP equipment?
Your quality assurance team assesses the impact and, if needed, opens a deviation or a change control. To support it, we provide a detailed report: cause of the failure, parts and materials used, welds performed and condition of the equipment when returned to service.
Welding — Pharmaceutical
What welding is used for pharmaceutical piping and equipment?
TIG welding on 316L stainless steel, with inert-gas back purging, produces smooth, clean joints on the inside. The ASME BPE standard is the reference for bioprocessing equipment. A weld log can be kept on request.
What is passivation and why do it after welding?
Passivation is a chemical treatment that restores the protective layer of stainless steel after welding and grinding. It reduces the risk of rust and contamination.
Hot work permit — Pharmaceutical
How is hot work carried out near a cleanroom?
Welding and grinding generate particles. The area must be isolated in agreement with your quality assurance team, then cleaned and disinfected according to your procedures before work resumes. The usual fire rules also apply: permit, clearing of combustibles and fire watch.
What does a hot work permit contain?
The location and validity period (no longer than the work shift), a description of the work, the checks made before starting, the name of the fire watch and the signatures. Combustible materials are removed or protected within a 15 m radius. After the work, the fire watch stays in place for at least 1 hour, then the area is checked periodically for at least 4 hours in total. You can download our template below. Discover: industrial maintenance and industrial staffing.
Permit templates to download
Sources
- Health Canada — Good manufacturing practices (GMP) guidelines, GUI-0001
- ASME BPE — Bioprocessing Equipment (sanitary and pharmaceutical equipment)
- Règlement sur la santé et la sécurité du travail (Regulation respecting occupational health and safety) (RSST), CQLR c. S-2.1, r. 13 — lockout (ss. 188.1 to 188.13), confined spaces (ss. 297 to 312), fall protection (ss. 33.2, 33.3 and 346 to 354)
- ASP Construction — Hot work permit (template, 2023)
- NFPA 51B — Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
- CSA W117.2 — Safety in welding, cutting and allied processes